Klabin postpones the startup of the first stage of Puma II until the second 2 weeks of August
Aug, 05, 2021 Posted by Ruth HollardWeek 202131
Klabin announced this Thursday that the scheduled date to begin the first stage of the Puma II Project has been changed to the second half of August.
Previously, this move was planned for the second half of July.
“This change is due to specific contingencies in the commissioning processes and pre-operational tests, and does not change the total investment foreseen for the project”, he explained in a relevant fact to the Securities Commission (CVM).
The Puma II Project, approved in 2019, will expand the capacity in the packaging paper segment through the construction of two paper machines with integrated pulp production at the Puma industrial unit in Ortigueira (PR).
Source: Money Times
To read the full original article, visit the link:
-
Ports and Terminals
Aug, 03, 2022
0
Anymal: Port of Tubarão recruits a special maintenance assistant
-
Coffee
Feb, 10, 2023
0
Brazil starts 2023 with a drop in coffee exports
-
Meat
Oct, 13, 2023
0
Brazilian Chicken Meat Industry Soar with 6.5% Export Growth
-
Ports and Terminals
Nov, 21, 2021
0
ANTAQ auctions areas in the ports of Santos (SP) and Imbituba (SC) for more than R$ 550 mi