Suzano shuts down Aracruz production line for 45 days for repairs
Sep, 02, 2022 Posted by Gabriel MalheirosWeek 202235
Suzano announced on September 01 that it is shutting down for about 45 days its production line A in Aracruz for “repairs in the recovery boiler.”
The intervention is part of a measure package announced by the company at the end of 2019, involving factory adjustments to replace parts of the recovery boiler and install crystallization systems.
In a statement, Suzano said that the shutdown would not affect customer service or its commercial strategy.
The total investment in the project is roughly 298 million reais, with 188 million already invested as of July.
Source: Money Times
To read the full original article, please go to: https://www.moneytimes.com.br/suzano-suzb3-paralisa-linha-de-producao-aracruz-por-45-dias-para-manutencao/
Related Post
-
Ports and Terminals
Nov, 04, 2019
0
New port could be built at Balneário Barra do Sul
-
Other Cargo
Jan, 20, 2022
0
Brazilian wineries register an increase of 83.25% in exports and sales reach 53 countries
-
Ports and Terminals
Jul, 05, 2019
0
New TCP Berth to operate with 12.5 m draft
-
Nov, 27, 2020
0
Brazilian fruit exports to Arab countries expected to grow in 2021