VLI’s rail terminal in Palmeirante to run operational tests in August
Aug, 09, 2022 Posted by Gabriel MalheirosWeek 202232
VLI will run the first operational tests on its new fertilizer hub at the Palmeirante Terminal, Tocantins. The structure’s construction began in the second half of 2021 in partnership with Copi, the company that manages the Port of Itaqui. Copi is in charge of the building and operations at the railway terminal connected to the coast.
The fertilizer hub centered at the Palmeirante terminal is strategically important for cargo movement in so-called Brazil’s Northern Arc considered the new national agricultural frontier.
The facility is currently at an advanced level, with almost 70% of the construction finished, including a balloon loop, railway tracks, and a 60,000-ton unloading and storage hopper. Fertilizers will be transported from the port at São Luís (MA) to Palmeirante (TO), supplying Tocantins, the northeast part of Mato Grosso, Pará, and Piauí.
According to VLI’s commercial manager for agribusiness and liquid bulk, Gabriel Fonseca, this project brings several benefits to the state. “The new fertilizer corridor can supply a highly productive region, in addition to being a seed for the development of an industrial hub,” he highlights.
-
Trade Regulations
Mar, 23, 2020
0
Trade balance registered US$1.4 billion surplus in third week of March
-
Ports and Terminals
Sep, 15, 2022
0
Largest ever fertilizer shipment arrives at Port of Santos, says Wilson Sons
-
Ports and Terminals
Jul, 01, 2022
0
Brazilian Air Force plans to cede area to new terminal in the Port of Santos
-
Grains
Oct, 11, 2022
0
Brazil wheat imports set to grow despite harvest advances