Port of Santos STS33 lease remains unresolved as contract is extended for 17th time
Sep, 03, 2026 Posted by Gabriel MalheirosWeek 202635
The long-delayed Port of Santos STS33 lease has led the Santos Port Authority (APS) to sign a new one-year transition contract for the area, extending for the 17th time the uncertainty surrounding the site.
The STS33 area, also known as SSZ 33E, covers 51,400 square meters in Jabaquara, in Santos, and has been occupied by Transbrasa since the 1990s. The new transition contract has been in force since August 24.
The federal government has authorized the area’s lease, but the city of Santos wants to use the site for a social housing project, adding another layer of complexity to the future of the port-linked land.
Although public consultation and a public hearing were held between March and June, APS, which is responsible for the auction, said in a statement that the contributions received are still being consolidated and technically reviewed.
“Responses to the questions will be made available on the company’s official website, with publication expected in September,” APS said.
The port authority did not set a date for the auction, saying only that it will be held “in due course,” after Brazil’s audit court TCU completes the mandatory prior review of the updated documents, including the public consultation contributions.
“There is no delay or problem preventing the auction, but rather full compliance with the mandatory procedural rite,” APS said.
Transition arrangement keeps dragging on
The current transition agreement with Transbrasa is the 17th since April 2018, when the first contract was signed. According to APS, 15 of those agreements had 180-day terms, while two were valid for up to one year or until the conclusion of the respective tender, whichever came first.
In practice, the area had two transition contracts per year until last year. APS said there is no defined limit on renewals.
“The new transition contract was signed with Transbrasa to avoid leaving the area idle and to ensure the continuity of activities during the period needed to conclude the tender, contributing to the maintenance of jobs and allowing APS to continue receiving property and tariff revenues,” the port authority said.
Transbrasa, when contacted, said it would not comment on the matter.
Land swap under discussion
In a statement, the Santos city government said the Jabaquara area is classified as a Special Zone of Social Interest, known in Brazil as Zeis, even though it lies within the Port of Santos polygon.
Cohab Santista, the local housing company, has prepared a study for the land currently occupied by Transbrasa, including the possible construction of 940 social housing units, according to the city administration.
“Together with the Santos Port Authority, the municipality has been working to find a solution that meets the needs of residents of Vila dos Criadores, in Alemoa, and moves back-port activities to a more appropriate location,” the city said.
The idea publicly discussed by APS has long been a land swap. Transbrasa’s operations — or those of whichever company wins the future auction — would be moved to Vila dos Criadores, while residents of that area would be relocated to the land in Jabaquara.
For that to happen, the Alemoa area must be included in the Port of Santos polygon, which still has not been authorized by Brazil’s ports and airports ministry MPor.
“At this time, the municipality is awaiting a response from the 1st Public Treasury Court regarding the considerations presented by the Port of Santos for the inclusion of Vila dos Criadores in the port polygon, which would make the land swap possible, with port operations transferred inside the polygon,” the city said.
APS authority over the lease
In March 2024, Brazil’s waterway regulator Antaq assigned APS the authority to review the lease model for STS33.
APS has been allowed to decide on port leases since December 2023, when a federal delegation agreement was signed.
Another 12 years?
APS said that when Complementary Law 1187/2022 was published, setting rules for land use and occupation in Santos’ island area, municipal legislation established a 15-year limit for port and back-port activities to remain in zones that had taken on a residential profile, such as Jabaquara.
“The draft tender notice made available for public consultation set a maximum contract term of 12 years, precisely reflecting the time remaining to comply with the legal requirement, expressly respecting the limit for maintaining port activities at the location determined by municipal zoning,” APS said. “This legally ensures that the land will be released within that maximum period for the city’s projects.”
Even so, the state-owned port authority said it does not expect the process to take that long.
“The intention of the current administration is to carry out a land swap with the winning bidder, transferring the operation to a more profitable area closer to the quay. If the swap takes place, that possibility must be included in the contract to be signed.”
The unresolved Port of Santos STS33 lease highlights the pressure around scarce port land in Brazil’s largest port complex, where logistics needs, urban planning and social housing demands increasingly overlap.
Source: A Tribuna
-
Ports and Terminals
Mar, 22, 2021
0
Brazil`s port terminals ranked by container handling: January 2021 vs. January 2020
-
Ports and Terminals
Oct, 15, 2024
0
New Santos Port Container Terminal Project Gets Green Light After Years of Delays
-
Ports and Terminals
Jul, 25, 2025
0
Trump tariffs stall 1,500 containers at Brazil’s Port of Vitória
-
Meat
Aug, 04, 2023
0
BRF closes joint venture with halal meat company in Saudi Arabia