Brazil audit court TCU orders changes to Santos port fuel terminal auction
Aug, 26, 2025 Posted by Sylvia SchandertWeek 202536
The Federal Audit Court (TCU) has ordered the Santos Port Authority (APS) to make a series of adjustments to the bidding notice for the STS08 terminal at the Port of Santos. The measures are necessary for the auction process to proceed.
STS08 is a 152,300-square-meter area in Alemoa, designated for handling, storage, and distribution of liquid bulk, particularly fuels.
The court determined that the project’s economic-financial model and draft contract must be aligned with the completion schedule of Alemoa’s new pier, which Petrobras is obliged to deliver under lease contract 06/2022. The aim is to avoid conflicts during the transition of liquid bulk operations.
Source: A Tribuna
Related Post
-
Economy
Jan, 14, 2026
0
World Bank cuts Brazil GDP forecast for 2026 to 2%
-
Economy
Mar, 17, 2022
0
OECD: Even if Latin America sells more commodities, the war’s impact is negative nonetheless
-
Fruits
Mar, 02, 2026
0
How watermelon producers are working to quintuple exports by 2030
-
Ports and Terminals
Feb, 25, 2022
0
A new port on the banks of São Gonçalo possibly on the make