Brazil audit court TCU orders changes to Santos port fuel terminal auction
Aug, 26, 2025 Posted by Sylvia SchandertWeek 202536
The Federal Audit Court (TCU) has ordered the Santos Port Authority (APS) to make a series of adjustments to the bidding notice for the STS08 terminal at the Port of Santos. The measures are necessary for the auction process to proceed.
STS08 is a 152,300-square-meter area in Alemoa, designated for handling, storage, and distribution of liquid bulk, particularly fuels.
The court determined that the project’s economic-financial model and draft contract must be aligned with the completion schedule of Alemoa’s new pier, which Petrobras is obliged to deliver under lease contract 06/2022. The aim is to avoid conflicts during the transition of liquid bulk operations.
Source: A Tribuna
Related Post
-
Ports and Terminals
Oct, 18, 2021
0
FT: Port delays complicating post-pandemic bottlenecks
-
Mar, 02, 2026
0
Paraná ports nearly quadruple barley and malt imports as brewing sector expands
-
Meat
Oct, 19, 2021
0
120 animals to be slaughtered in Ceará swine fever region
-
Shipping
Nov, 07, 2024
0
TLP1: Service switches Callao stop to Chancay, adds call in Lirquén and San Antonio (Chile)