APS launches tender for structural reinforcement and draft increase at Barnabé Island quay
Jun, 24, 2025 Posted by Denise VileraWeek 202526
On Monday (June 23), the Santos Port Authority (APS) published Tender Notice No. 40/2025 for the contracting of specialized services to reinforce the quay at Barnabé Island structurally. The works, scheduled for execution over 21 months, aim to adapt the terminal to accommodate larger vessels.
The services include structural reinforcement of the quay and the four existing mooring dolphins, pile repair, and an increase in operational draft from -10.0m to -15.0m. The basic project also includes the installation of a new dolphin, fenders, and metal gangways, as well as the construction of two oil-water separators for wastewater treatment.
APS has also made public seven other tender notices in recent weeks for the procurement of equipment for APS substations, road signage, air transport services, and ballistic vests for the Port Guard, among others. The tenders are available for consultation on the tenders page of the company’s website.
See a summary of each tender notice below:
Tender No. 35/2025
Object: supply, on demand, of veterinary supplies
Contract term: 12 months
Proposal deadline: by 10:00 a.m. on 07/01
Tender No. 36/2025
Object: provision of air transport services using a twin-engine helicopter
Contract term: 12 months
Proposal deadline: by 10:00 a.m. on 07/08
Tender No. 37/2025
Object: supply of power cables, medium-voltage circuit breakers, power transformers, medium-voltage cable splices, and other special equipment aimed at improving operational efficiency and safety conditions at electrical substations
Contract term: 180 days
Proposal deadline: by 10:00 a.m. on 07/02
Tender No. 38/2025
Object: supply of office materials to meet the needs of the Port of Itajaí – APS Branch
Contract term: 3 months
Proposal deadline: by 10:00 a.m. on 07/04
Tender No. 39/2025
Object: service for maintenance and implementation of vertical and horizontal road signage on both banks of the Port of Santos and in areas under APS responsibility
Contract term: 20 months
Proposal deadline: by 10:00 a.m. on 07/14
Tender No. 40/2025
Object: execution of structural reinforcement of the quay and existing dolphins, structural repair of the quay’s sheet piles to increase the draft of the operational quay at Barnabé Island; installation of new fenders, a new dolphin, metal gangways between dolphins, and two oil-water separator boxes at the quay ends
Contract term: 26 months
Proposal deadline: by 10:00 a.m. on 07/15
Tender No. 41/2025
Object: supply of external ballistic vest covers for the Port Guard Superintendent
Contract term: 12 months
Proposal deadline: by 10:00 a.m. on 07/04
Tender No. 42/2025
Object: supply of materials and equipment for the Armament Control, K9 Unit, and Maritime Patrol Sectors of the Operations Management Department
Contract term: 12 months
Proposal deadline: by 10:00 a.m. on 07/03
-
Ports and Terminals
Nov, 06, 2023
0
Brazilian Police bust 1.5 tonnes of cocaine aboard ship in Port of Vitoria
-
Grains
Sep, 27, 2022
0
Brazil: sept corn shipments exceed 5mt to date
-
Economy
Dec, 30, 2021
0
Arab countries double their exports to Brazil
-
Ports and Terminals
Apr, 20, 2023
0
Itajaí port complex sees 1.4 million cargo throughput in March