Portonave resumes two-vessel berthing after new quay section opens
Aug, 19, 2026 Posted by Gabriel MalheirosWeek 202634
Portonave has resumed simultaneous berthing of two vessels at its Navegantes container terminal after delivering another 250-meter section of its quay reinforcement and upgrade project.
With the new section now available, the terminal has 700 meters of operational quay. The expanded berth availability is expected to improve agility and productivity in port operations.
Since January 2024, when the quay works began, the terminal had been receiving only one vessel at a time. The new section was released for operations on August 18, when the CMA CGM Thorium and Mercosul Suape operated simultaneously.
Once the full quay project is completed, Portonave will be able to receive up to three vessels at the same time.
Designed for the newest generation of vessels, the upgraded quay will be able to berth ships up to 400 meters long, the size of the most modern containerships, provided the access channel and turning basin are also adapted.
From now on, vessels can be handled simultaneously, without having to wait for a berth position to be released. The result is faster operations, more efficient service for carrier calls and better use of the terminal’s infrastructure.
The delivery of this section marks the final stretch of Portonave’s quay upgrade project, which had reached 92% completion by July. The remaining phase is expected to be completed in the fourth quarter of 2026.
The improvements also prepare the quay for the installation of shore power infrastructure, a system that will allow docked vessels to receive electricity from land and eliminate fuel burning while they remain at the terminal.
Electric equipment strengthens efficiency plan
The quay upgrade is part of a broader efficiency and sustainability plan that, together with new equipment, exceeds R$2 billion in investment.
Equipment alone accounts for about R$500 million in fully electric units, in line with the company’s decarbonization strategy.
By the end of the plan, the terminal will have eight ship-to-shore cranes, 32 rubber-tired gantry cranes, seven reach stackers, 61 terminal tractors and four scanners. All new equipment will be fully electric.
The new equipment includes:
- Two electric ship-to-shore cranes, or e-STS units, used to move containers between ship and quay. They will be the first cranes of this size in Brazil. Investment totals R$229 million, with arrival expected later this year.
- Fourteen electric rubber-tired gantry cranes, or e-RTGs, used for yard handling and stacking. Investment totals R$210 million. They arrived in July 2026 and are scheduled to enter operation from August.
- Thirty electric terminal tractors and six electric reach stackers, used for container transport and handling in the yard. Investment is approximately R$61 million. Delivery will be gradual, with all machines operating by January 2027.
- Two scanners for cargo inspection and container handling. Investment totals R$25 million. The units have been operating since 2025.
Portonave grows during quay works
Despite the ongoing construction work, the terminal continues to grow.
By the end of July 2026, Portonave had handled 750,571 TEUs, up 21.3% from the same period in 2025.
The performance underscores the terminal’s ability to maintain productivity during a major infrastructure intervention and points to the operational gains expected once the works are completed in the coming months.
Environmental compensation in Navegantes restinga area
As environmental compensation for the quay upgrade, Portonave is carrying out a recovery plan for a degraded permanent preservation area along the Navegantes waterfront.
The initiative will restore about 40,000 square meters of restinga vegetation in the Meia Praia neighborhood, with the planting of native species from the coastal ecosystem and control of invasive exotic species.
The work is being monitored by the Navegantes Environmental Institute and Santa Catarina’s environmental agency IMA.
Source: Informativo dos Portos
-
Grains
Sep, 19, 2023
0
Brazil’s Northeastern corn exports soar, outpacing national growth
-
Meat
Jul, 28, 2021
0
MAPA: China has requested updated information on 56 cold-storage plants waiting for licenses
-
Grains
Nov, 17, 2022
0
Brazil’s soybean exports to reach 78 million tonnes in 2022
-
Ports and Terminals
Nov, 08, 2023
0
São Francisco do Sul Takes Lead Among Brazil’s Santa Catarina Ports