After completing the first stage of the paving work on the internal roads of the Port of Rio Grande, Portos RS will begin this month to complement this important structural intervention that will allow for improved mobility in the commercial public wharf. The tender for carrying out the work was won by the company Compacta Sul Pavimentação and the forecast for completion of the activities is seven months.
The transformation that has been promoted in the infrastructure of the Port of Rio Grande became possible from the implementation of a public company model that allowed better management and application of resources in structuring jobs. To carry out the services, Portos RS will make an investment of almost R$ 10 million.
As part of the project, the Infrastructure Board foresees the construction of 1,200 meters of drainage network, which will optimize the drainage of rainwater, and the installation of water, oil and solid particle retention tanks. The contract also includes paving, with reinforcement of the subgrade, roads and maneuvering areas, which will be added to the work already carried out and will total an area of 40,000 square meters.
Also included in the improvement package are the vertical and horizontal signaling of the benefited areas and the requalification of the washing ramp and equipment.
-
Ports and Terminals
May, 18, 2023
0
Brazil: Porto Itapoá now served by FIL service from HMM
-
Ports and Terminals
Feb, 23, 2022
0
Localfrio breaks import record at Itajaí terminal
-
Ports and Terminals
Nov, 03, 2023
0
Another Record: Itaqui Port Achieves Best-Ever Month for Cargo Movement
-
Other Logistics
Jul, 04, 2023
0
Brazil announces another section of FIOL railroad under construction